We received our building permit last week, exterior improvements are underway, and we will begin the interior work soon. Lots to do: a new trench drain with a pitched floor, boiler room, malt storage room, new restrooms, upgraded electrical system and plumbing, etc., etc. A little daunting, but here we go!
We also received news that our custom brewery equipment is now under construction, and it all should arrive in mid-October. That should give us enough time to brew up some holiday cheer.